Megawattlas

Data centers in India

308 facilities across 55 cities, from Mumbai's carrier hotels to gigawatt campuses announced for Hyderabad and Visakhapatnam.

Sheet 03-IN · India

Facilities
308
Operators
92
Mapped
82 of 308
Snapshot
2026-10-17
255operational in India
1,581 MWpublished by 88 operating sites
43 · 2,537 MWbeing built
10 · 3,771 MWannounced
15°N20°N25°N30°N75°E80°E85°E90°E0500 km
  • Operational
  • Under construction
  • Announced (hollow)
India: 82 of 308 facilities have published coordinates and are plotted (27%). Mercator projection; extent of plotted sites 28.64°N 72.51°E to 12.84°N 91.79°E. Scale bar true at the sheet's centre. Contours mark where India's mapped sites cluster most tightly. Pan and filter them on the interactive map.

Reading India's numbers

India is the second-largest country in the atlas after the United States, with 308 facilities run by 92 operators. The base is spread over 55 cities but leans heavily on one region. The Mumbai metropolitan region, which here joins Mumbai, Navi Mumbai and Thane, holds 92 facilities, 30% of the national total, and 2,401 MW of published capacity. After it come Chennai (34), Delhi NCR (32), Bengaluru (24), Hyderabad (21), Pune (16).

Counting megawatts rather than buildings changes the picture. Only 88 of India's 255 operating facilities publish a capacity, together 1,581 MW. Many of the rest are carrier and exchange sites: the 11 National Internet Exchange of India nodes in the table, for example, state no power figure at all. Projects under construction publish 2,537 MW and announced ones 3,771 MW, so the published pipeline is about 4.0 times the published operating base. The median Indian project under construction states 49 MW; the median operating site that publishes a number states 10 MW.

From Mumbai to Hyderabad and Vizag

New capacity is not landing where the old capacity sits. Hyderabad has fewer facilities than Chennai but the largest published capacity of any Indian city, 2,027 MW, carried by 3 projects of 200 MW or more: HyperVault Future City Campus (1,000 MW), AdaniConneX Hyderabad (600 MW), AirTrunk HYD1 (243 MW). Visakhapatnam on the east coast appears only once in the catalogue, yet that single record, Colt DCS / RMZ Visakhapatnam Digital Campus, is the largest published project in the country at 1,250 MW. The two largest of these, the HyperVault and Visakhapatnam campuses, are announced rather than under construction, and phased campuses of this size usually take several years to reach full load.

One correction is applied on this page: the source catalogue listed TCS's HyperVault campus in Hyderabad twice, citing the same press release and the same 1,000 MW. The atlas counts it once, which is why India's announced total here is 3,771 MW rather than 1,000 MW higher.

Who is building

By number of sites the market is led by colocation specialists: ST Telemedia's Indian business has 34 facilities and 635 MW published, Nxtra Data 24, and NTT 20. The pipeline belongs to a different kind of player. AdaniConneX has just 5 records, but 2,033 MW of published capacity, more than any other operator in India. 3 Indian projects publish 1 GW or more, and 2 of them come from groups that belong to the Adani and Tata conglomerates.

Power and policy

The national average business electricity price in the atlas's power dataset is $0.109 per kWh, but tariffs are set by state. Maharashtra, home to the Mumbai cluster, has cut high-tension industrial rates and reclassified data centers as industrial consumers, and Tamil Nadu's industrial tariff rose only modestly this year, so both main hubs sit at or below that average. State policy is the main incentive layer: Uttar Pradesh, which includes Noida and Greater Noida, offers a ten-year electricity duty exemption and capital subsidies under its 2026 data centre policy, and Tamil Nadu exempts data centres from electricity tax for five years. At national level, the Union Budget 2026–27 proposes a tax holiday until 2047 for foreign cloud providers serving global customers from Indian data centres; it is listed as proposed, not yet in force. Unlike Malaysia or parts of the United States, India has no data center moratorium or grid-connection cap in the atlas's restrictions dataset.

Comparing colocation in Mumbai, Chennai or Hyderabad rather than tracking projects? Published rack and power prices, and a quote request, are at wattandrack.com.

Who operates data centers in India

OperatorFacilitiesPipelineCitiesPublished MWSites with MW
ST Telemedia Global Data Centres (India)341211634.632/34
Nxtra Data24011234.219/24
NTT Global Data Centers2047300.614/20
Sify Technologies14012120.78/14
CtrlS Datacenters13210251.910/13
Iron Mountain1337161.710/13
National Internet Exchange of India11010not published0/11
NTTCINS906not published0/9
D-VoiS Broadband808not published0/8
Equinix603not published0/6
BSNL (Dimension Data)606not published0/6
TATA Communications606not published0/6
Reliance Communications604not published0/6
AdaniConneX5452,0335/5
Yotta Data Services5241713/5
Colt Data Centre Services / RMZ1111,2501/1
HyperVault (TCS)1111,0001/1
Princeton Digital Group4334324/4
AirTrunk2223712/2

19 of 92 operators shown: the largest by number of facilities, plus any of the six largest by published MW. "Pipeline" counts sites under construction or announced.

India by city and metro

City / areaFacilitiesOperationalPipelinePublished MW
Mumbai50437712.3
Navi Mumbai4130111,688.4
Chennai34268898.9
Bengaluru2423186.4
Hyderabad211472,026.5
Noida21165376
Pune16151382.1
Kolkata129350.2
New Delhi10100—
Delhi77012
Jaipur5506
Manesar44033.5
Ahmedabad43113.2
Patna43112.1
Bhubaneswar4401.8
Visakhapatnam3121,250
Jamnagar, Gujarat321168
Lucknow3300.2
Greater Noida22030
GIFT City2201
Gurugram220—
Indore211—
Mangalore220—
Metro groupingFacilitiesPublished MW
Mumbai metropolitan region922,400.7
Delhi NCR32418

32 further locations in India have one facility each: Vijayawada (Mangalagiri), Panchkula, Sriperumbudur, Faridabad, Ghaziabad, Ludhiana, Secunderabad, Bhiwadi, Mohali, Nashik, Kochi, Raipur, Sonipat, Gurgaon Haryana, Chandimandir Cantonment, Udhampur, Bengaluru Urban, Gautam Budh Nagar, Airoli Naka, Navi Mumbai, Mysuru, Vadinar, Navi Mumbai, Thane, GIFT City, Gandhinagar, Cochin, Manipal, Gurgaon, Nanakaramguda, Thane, Kalyan, Kanpur, Guwahati, SALEM. Metro groupings join neighbouring cities the way the market refers to them: Mumbai metropolitan region = mumbai, navi-mumbai, thane; Delhi NCR = noida, delhi, gurugram, greater-noida.

India: projects under construction and announced

ProjectOperator / developerCity / areaMWStatus
Colt DCS / RMZ Visakhapatnam Digital CampusColt Data Centre Services / RMZVisakhapatnam (Vizag)1,250Announced
AdaniConneX Navi MumbaiAdaniConneXNavi Mumbai1,000Announced
HyperVault Future City CampusHyperVault (TCS)Hyderabad (Telangana Future City)1,000Announced
AdaniConneX HyderabadAdaniConneXHyderabad600Under construction
AdaniConneX PuneAdaniConneXPune250Announced
AirTrunk HYD1AirTrunkHyderabad243Under construction
Meta-Reliance AI Data Center JamnagarReliance Industries (built-to-suit for Meta)Jamnagar, Gujarat168Under construction
AdaniConneX NoidaAdaniConneXNoida150Under construction
Yotta Chennai Data Center ParkYotta Data ServicesChennai140Announced
AirTrunk MAA1AirTrunkChennai128Under construction
PDG MU2 Navi MumbaiPrinceton Digital GroupNavi Mumbai120Under construction
Colt Chennai Data CentreColt DCSChennai (Ambattur)96Announced
PDG HY1 HyderabadPrinceton Digital GroupHyderabad90Under construction
Iron Mountain MUM-3Iron MountainMumbai85Under construction
PDG CH1 ChennaiPrinceton Digital GroupChennai72Under construction
STT Palava 4ST Telemedia Global Data Centres (India)Mumbai (Palava)60.5Under construction
STT Palava 5ST Telemedia Global Data Centres (India)Mumbai (Palava)60.5Under construction
Pi Amaravati Data CenterPi Data CentersVijayawada (Mangalagiri)60Under construction
CapitaLand Data Centre Navi Mumbai Tower 2CapitaLand India TrustNavi Mumbai55Under construction
NTT Noida 2 Data CenterNTT Global Data CentersNoida52.8Under construction
STT Palava 1ST Telemedia Global Data Centres (India)Mumbai (Palava)50Under construction
Anant Raj Cloud PanchkulaAnant Raj Cloud (Ashok Cloud)Panchkula50Under construction
STT Palava 1ST Telemedia Global Data Centres (India)Mumbai (Palava)50Under construction
STT Navi Mumbai 2ST Telemedia Global Data Centres (India)Navi Mumbai (MIDC Mahape)49Under construction
STT Navi Mumbai 3ST Telemedia Global Data Centres (India)Navi Mumbai (MIDC Mahape)42Under construction
Digital Connexion BOM10Digital ConnexionMumbai40Under construction
CapitaLand Data Centre ITPH, HyderabadCapitaLand India TrustHyderabad40Under construction
STT Navi Mumbai 4ST Telemedia Global Data Centres (India)Navi Mumbai (MIDC Mahape)36Under construction
NTT Chennai 2 Data CenterNTT Global Data CentersChennai34.8Under construction
Techno Digital NoidaTechno Digital (Techno Electric)Noida30Under construction
STT Noida 3ST Telemedia Global Data Centres (India)Noida28Under construction
STT Navi Mumbai 1ST Telemedia Global Data Centres (India)Navi Mumbai (MIDC Mahape)28Under construction
Iron Mountain CHN-1Iron MountainChennai23.2Under construction
Colt Mumbai 1 & 2 Data CentresColt DCSNavi Mumbai22Announced
STT Noida 2ST Telemedia Global Data Centres (India)Noida22Under construction
Iron Mountain CHN-2Iron MountainChennai19Under construction
STT Chennai 4ST Telemedia Global Data Centres (India)Chennai (Ambattur)17Under construction
Techno Digital KolkataTechno Digital (Techno Electric)Kolkata13Announced
CtrlS Patna Edge Data Center (DC2)CtrlS DatacentersPatna11.6Under construction
CtrlS Ahmedabad Edge Data CenterCtrlS DatacentersAhmedabad9.2Under construction
STT Kolkata 2ST Telemedia Global Data Centres (India)Kolkata (New Town)6Under construction
Pi Data Centers Central MumbaiPi Data CentersMumbai3Under construction
Pi Data Centers HyderabadPi Data CentersHyderabad3Under construction
AWS Bharat Future City Data CenterAmazon Web Services (AWS)Hyderabad (Bharat Future City)not publishedUnder construction
NTT Bengaluru 4 CampusNTT Global Data CentersBengalurunot publishedUnder construction
NTT Kolkata 1 CampusNTT Global Data CentersKolkatanot publishedAnnounced
Bridge Data Centres BBY01Bridge Data CentresNavi Mumbainot publishedUnder construction
Yotta NM2Yotta Data ServicesNavi Mumbainot publishedUnder construction
Google AI Hub VisakhapatnamGoogle / AdaniConneX / AirtelVisakhapatnam (Vizag)not publishedAnnounced
RackBank CEN1 (Raipur)RackBankRaipurnot publishedUnder construction
RackBank CEN2 (Indore)RackBankIndorenot publishedUnder construction
RackBank WST1 (Navi Mumbai)RackBankNavi Mumbainot publishedUnder construction
Anant Raj Cloud Rai (Sonipat)Anant Raj Cloud (Ashok Cloud)Sonipatnot publishedUnder construction

Electricity price for data centers in India

$0.109 per kWh (range $0.090–$0.140), business tariff. Commercial/industrial tariffs vary widely by state (GlobalPetrolPrices national average, Dec 2025). Maharashtra (MERC) cut HT-industrial rates ~15% for FY2025-26 with further annual declines planned through FY2029-30 and reclassified data centers as industrial consumers; Tamil Nadu's FY2026 industrial tariff rose just 3.16% to ~₹7.5/kWh (~$0.087) — both DC-hub states now sit mid-range or below this average, not above it. Open-access renewables PPAs are common for DCs.

India: incentives and restrictions

Union Budget 2026–27 tax holiday for foreign cloud providers using India-based data centres · Proposed · until 2047

Tax holiday until 2047 for eligible foreign cloud service providers serving global customers from data centres located in India. Eligibility framework covers notified foreign entities, use of Indian data centres and an Indian reseller for services to domestic customers; a 15% safe harbour margin is proposed for related data centre entities. (Ministry of Finance, Government of India)

Uttar Pradesh Data Centre Policy 2026 · Active · Uttar Pradesh

100% electricity duty exemption for 10 years, 100% stamp duty exemption on land from government authorities, capital subsidy up to ₹20 crore for units and interest subsidy up to ₹50 crore for parks. Data Centre Parks: minimum 40 MW total load. Data Centre Units: more than 2 MW and less than 40 MW. Edge: at least 10 edge data centres of 50 kW each, 2 MW cumulative. An earlier Uttar Pradesh Data Centre Policy 2021 is published on the same portal. (Invest UP, Government of Uttar Pradesh)

Tamil Nadu Data Centre Policy 2021 · Active · Tamil Nadu

100% electricity tax exemption for 5 years for data centres. (Guidance Tamil Nadu)

Datasets behind this page: facility count (308 facilities); operators table (92 operators); mw pipeline (43 projects with published MW); power tariff (India $0.109/kWh); metros / cities (55 cities, 2 metro groupings); incentives / restrictions (3 incentives, 0 restrictions). How they are compiled: methodology. Sources: see Sources.