Data centers in Malaysia
83 facilities, almost a third of them still being built or planned, split between the Klang Valley and a fast-growing Johor corridor facing Singapore.
Sheet 03-MY · Malaysia
- Facilities
- 83
- Operators
- 46
- Mapped
- 8 of 83
- Snapshot
- 2026-10-17
- Operational
- Under construction
- Announced (hollow)
Two corridors and a tighter approval regime
Malaysia has 83 facilities in the atlas, and 26 of them, 31%, are still under construction or announced. That is a far younger stock than India's (17% in the pipeline) or Australia's (13%). The country splits into two corridors. The Klang Valley grouping, Kuala Lumpur with Cyberjaya, Shah Alam and their neighbours, has 52 facilities. The Johor grouping, across the causeway from Singapore, has 25.
Published capacity runs the other way. Johor's facilities state 2,829 MW between them against 1,035 MW for the Klang Valley: fewer sites, much larger ones. Kulai alone has 7 records and 1,468 MW, led by YTL Green Data Center Park (500 MW, under construction) and PDG JH2 (300 MW, announced) and GDS at YTL Green Data Center Park (168 MW, announced).
A caution on Kulai: GDS at YTL Green Data Center Park (168 MW) is described by its source as a development within the YTL Green Data Center Park (500 MW). The two records cite different announcements and are kept separate, but the GDS phase may be part of the park's headline figure, so Kulai's total could overstate the site by up to 168 MW.
Cyberjaya: the established hub, re-sized
Cyberjaya is the densest single location in the country with 30 facilities, and Kuala Lumpur proper adds 12. 23 of Cyberjaya's sites are operating; AIMS Data Centre has the most records of any operator in Malaysia (7). The new projects are of another scale; operating Cyberjaya sites that publish a figure have a median of 8 MW, while the largest projects state Vantage Cyberjaya II Campus (256 MW), AIMS 200MW AI Data Centre Cyberjaya (200 MW), EdgeConneX Cyberjaya Campus (200 MW). Among operators, the largest published totals belong to Vantage (587 MW) and AirTrunk (550 MW).
What the rules now favour
Malaysia's pipeline has grown while approvals tightened. Johor set up a vetting committee in June 2024 and by November that year had rejected nearly 30% of applications, partly because sites lacked adequate utilities. In November 2025 the state said it would no longer approve Tier 1 and Tier 2 data centres because of their water use, and new projects must source reclaimed water. In February 2026 the Prime Minister told parliament that applications unrelated to high technology and AI had already been stopped for almost two years. The incentive side points the same way: MIDA's Digital Ecosystem Acceleration Scheme gives digital infrastructure providers a 100% investment tax allowance for up to ten years, open until 2027, provided projects meet the national sustainable data centre guidelines. The result is visible in the data: 15 of the 26 Malaysian projects in the pipeline are flagged AI-ready by their sources.
Power
Electricity comes from Tenaga Nasional (TNB) under its 2025–2027 regulatory period. The power dataset puts the all-in business price at about $0.135 per kWh: a base commercial tariff plus a monthly fuel surcharge, sales tax and a renewable-energy levy. Two recent statements show how large the loads have become. DayOne / TNB Power Generation (2026-08-07): MOU to explore up to 1.5 GW of dedicated on-site generation for DayOne's planned Sepang, Selangor campus. DayOne (2026-10-14): DayOne upsized its Malaysia syndicated financing to about $7.2B and reported billings above 1GW and bookings of about 2.3GW. DayOne's Malaysian campuses are not yet individual rows in the facility table, so its capacity appears here only through these statements.
Only 8 of Malaysia's 83 facilities have published coordinates, so the map below shows a small part of the market; the city tables are the better guide.
Because new approvals now go mainly to AI workloads, much of this capacity will be sold as GPU compute rather than racks. Rental prices for that compute and a census of AI campuses are tracked at computecensus.com.
Who operates data centers in Malaysia
| Operator | Facilities | Pipeline | Cities | Published MW | Sites with MW |
|---|---|---|---|---|---|
| AIMS Data Centre | 7 | 1 | 3 | 227.5 | 4/7 |
| Open DC | 5 | 0 | 4 | 5.3 | 2/5 |
| Bridge Data Centres | 5 | 2 | 4 | not published | 0/5 |
| NTT Global Data Centers | 4 | 0 | 1 | 13.5 | 2/4 |
| Equinix | 4 | 2 | 3 | not published | 0/4 |
| Vantage Data Centers | 3 | 1 | 2 | 587 | 3/3 |
| AirTrunk | 3 | 1 | 2 | 550 | 2/3 |
| EdgeConneX | 3 | 3 | 2 | 289 | 3/3 |
| STT GDC Malaysia (joint venture with Basis Bay) | 3 | 3 | 2 | 32.8 | 3/3 |
| YTL Data Center Holdings | 2 | 1 | 2 | 505 | 2/2 |
| Princeton Digital Group | 2 | 1 | 1 | 500 | 2/2 |
| Bitdeer AI (Bitdeer Technologies Group) | 2 | 2 | 2 | 125.1 | 2/2 |
| CSF Group | 2 | 0 | 1 | not published | 0/2 |
| Digital Realty | 2 | 0 | 1 | not published | 0/2 |
| TM Global (Telekom Malaysia) | 2 | 0 | 2 | not published | 0/2 |
15 of 46 operators shown: the largest by number of facilities, plus any of the six largest by published MW. "Pipeline" counts sites under construction or announced.
Malaysia by city and metro
| City / area | Facilities | Operational | Pipeline | Published MW |
|---|---|---|---|---|
| Cyberjaya | 30 | 23 | 7 | 848.3 |
| Kuala Lumpur | 12 | 7 | 5 | 181.5 |
| Iskandar Puteri | 9 | 4 | 5 | 750 |
| Johor Bahru | 8 | 5 | 3 | 611.4 |
| Kulai | 7 | 3 | 4 | 1,468 |
| Shah Alam | 6 | 5 | 1 | 5 |
| Penang | 3 | 3 | 0 | — |
| Kuching | 2 | 1 | 1 | 17 |
| Metro grouping | Facilities | Published MW |
|---|---|---|
| Johor | 25 | 2,829.4 |
| Klang Valley (Kuala Lumpur–Cyberjaya) | 52 | 1,034.8 |
6 further locations in Malaysia have one facility each: Bukit Kayu Hitam, Kedah, Petaling Jaya, Johor, Bandar Baru Bangi, Kajang, Brickfields. Metro groupings join neighbouring cities the way the market refers to them: Johor = johor-bahru, kulai, iskandar-puteri, johor; Klang Valley (Kuala Lumpur–Cyberjaya) = cyberjaya, kuala-lumpur, shah-alam, petaling-jaya, bandar-baru-bangi, kajang, brickfields.
Malaysia: projects under construction and announced
26 projects Clear filters
| Project | Operator / developer | City / area | MW | Status |
|---|---|---|---|---|
| YTL Green Data Center Park | YTL Data Center Holdings | Kulai | 500 | Under construction |
| PDG JH2 | Princeton Digital Group | Kulai | 300 | Announced |
| AirTrunk JHB3 & JHB4 | AirTrunk | Iskandar Puteri | 280 | Announced |
| Vantage Cyberjaya II Campus | Vantage Data Centers | Cyberjaya | 256 | Under construction |
| AIMS 200MW AI Data Centre Cyberjaya | AIMS Data Centre | Cyberjaya | 200 | Announced |
| EdgeConneX Cyberjaya Campus | EdgeConneX | Cyberjaya | 200 | Announced |
| TM Nxera Data Centre Campus — Iskandar Puteri | TM Nxera (Telekom Malaysia / Nxera-Singtel JV) | Iskandar Puteri | 200 | Under construction |
| Empyrion MY1 Johor Data Centre Campus | Empyrion Digital | Iskandar Puteri (Nusajaya, SiLC) | 200 | Under construction |
| GDS at YTL Green Data Center Park | GDS Holdings / YTL Power | Kulai | 168 | Announced |
| EdgeConneX Bukit Jalil | EdgeConneX | Kuala Lumpur | 70 | Under construction |
| Bitdeer AI A202 (Johor Campus) | Bitdeer AI (Bitdeer Technologies Group) | Johor Bahru | 65.1 | Announced |
| Epoch Digital Nusajaya Tech Park (Project Mercury) | Epoch Digital (Actis) | Johor Bahru (Nusajaya) | 60 | Under construction |
| Bitdeer AI A103 (Cyberjaya Campus) | Bitdeer AI (Bitdeer Technologies Group) | Cyberjaya | 60 | Announced |
| Pi DC1 | Pi Data Centre (PiDC Holdings / Jakel Group) | Cyberjaya | 51 | Under construction |
| EdgeConneX Kuala Lumpur CBD | EdgeConneX | Kuala Lumpur | 19 | Announced |
| FutureData Park, first data center (Global Telecommunications Group) | FutureData Sdn Bhd (TSG Group / Cyclect) | Kuching | 17 | Under construction |
| STT Johor 1 | STT GDC Malaysia (joint venture with Basis Bay) | Iskandar Puteri (Johor) | 16 | Under construction |
| EXSIM EX1 Data Center | Exsim Jalil Link Sdn. Bhd. (Exsim Group) | Kuala Lumpur (Bukit Jalil) | 15 | Under construction |
| STT Kuala Lumpur 1 | STT GDC Malaysia (joint venture with Basis Bay) | Kuala Lumpur (Cyberjaya) | 14 | Under construction |
| STT Cyberjaya DC.2 | STT GDC Malaysia (joint venture with Basis Bay) | Cyberjaya | 2.8 | Under construction |
| Bridge Data Centres MY07 | Bridge Data Centres | Johor Bahru | not published | Under construction |
| Equinix KL2 | Equinix | Kuala Lumpur | not published | Announced |
| Equinix JH2 | Equinix | Iskandar Puteri | not published | Under construction |
| Global Switch Johor | Global Switch | Kulai | not published | Announced |
| Bridge Data Centres MY03 | Bridge Data Centres | Kuala Lumpur (Bukit Jalil) | not published | Under construction |
| Google Elmina Data Center | Shah Alam (Elmina) | not published | Under construction |
Electricity price for data centers in Malaysia
$0.135 per kWh (range $0.120–$0.145), business tariff. TNB RP4 (2025-2027) base tariff — C1/C2 commercial 36.50 sen/kWh, E1 industrial 33.70 sen/kWh — plus a monthly AFA surcharge that peaked at +3.80 sen/kWh in August 2026 and has since eased for two straight months (Sept +3.67 sen; TNB's own Oct-Dec outlook: +3.36, +2.81, +5.48 sen), 6% SST and a 1.6% KWTBB levy; latest all-in GlobalPetrolPrices read is MYR 0.568/kWh (~$0.139).
Malaysia: incentives and restrictions
Digital Ecosystem Acceleration Scheme (DESAC) — Digital Infrastructure Providers · Active · until 2027-12-31
Investment tax allowance of 100% on qualifying capital expenditure, offset against up to 100% of statutory income for up to ten years. Open to Digital Infrastructure Providers such as data centres and submarine cables; projects must meet the Guidelines for Sustainable Development of Data Centres (December 2024). Applications to MIDA are accepted until 31 December 2027. (Malaysian Investment Development Authority (MIDA))
Johor sets up committee to vet data centre applications on water and power · In-force · 2024-06 · Johor
The state established a vetting committee in June 2024 to screen data centre proposals against sustainability and infrastructure requirements. By November 2024 it had rejected nearly 30% of applications, including 4 of 14 from overseas operators, partly because chosen sites lacked adequate utilities. (Johor State Government)
Johor halts approvals for Tier 1 and Tier 2 data centres over water use · In-force · 2025-11 · Johor
The chairman of Johor's housing and local government committee said the state will no longer approve Tier 1 and Tier 2 data centres because of their water consumption. New projects must source reclaimed water, keep distance from residential and commercial zones and pass five levels of vetting covering water, power and environmental criteria. (Johor State Housing and Local Government Committee)
Malaysia confirms new non-AI data centre applications have been stopped · In-force · 2026-02-24
Prime Minister Anwar Ibrahim told parliament that new data centre applications unrelated to high technology and AI had already been stopped for almost two years, while AI-related projects are approved more readily. The statement confirmed an informal screening criterion applied since around 2024. (Government of Malaysia (Prime Minister))
Capacity statements about Malaysia
- 2026-08-07 · DayOne / TNB Power Generation (Sepang, Selangor), 1,500 MW — on-site generation explored (MOU): MOU to explore up to 1.5 GW of dedicated on-site generation for DayOne's planned Sepang, Selangor campus.
- 2026-10-14 · DayOne (Johor), 1,000 MW — billings: contracted IT power generating income (company definition, over 1GW, all markets): DayOne upsized its Malaysia syndicated financing to about $7.2B and reported billings above 1GW and bookings of about 2.3GW.
Datasets behind this page: facility count (83 facilities); operators table (46 operators); mw pipeline (20 projects with published MW); power tariff (Malaysia $0.135/kWh); metros / cities (14 cities, 2 metro groupings); incentives / restrictions (1 incentives, 3 restrictions); capacity statements (2 statements). How they are compiled: methodology. Sources: see Sources.
Missing a project in Malaysia?
If you know of a Malaysia facility, expansion or proposal that is not listed, or a figure here is out of date, send it with a public source and we will update the page.